Rehabilitation of 600mm–800mm Sewer Line
Client: GMDA
Location: Sector 21/22/23, Gurugram
Desilting of existing master sewer line including plugging and diversion of flow, providing and installing of Cured –in – Place Pipe liner (CIPP) of existing deteriorated master sewer line for size 600mm, 700mm and 800mm i/d along dividing road of Sector – 21/22, 22/23 and 23/23A, Gurugram and all other works contingent thereto
Here the crown was totally corroded leading to structural loss of sewer and frequent settlement. Artificial supports were first inserted in to the existing pipe which was almost about the collapse (as shown in the picture) to make the CIPP process easier and more durable
Here the crown was totally corroded leading to structural loss of sewer and frequent settlement. Artificial supports were first inserted in to the existing pipe which was almost about the collapse (as shown in the picture) to make the CIPP process easier and more durable


Condition of the sewer revealed after desilting/cleaning